Document ID: RM-GA-P3 File Path: docs/18-roadmap/v1.0/phase3-scale-distribution-tickets.md Version: 1.4.0 Status: Track A (GA) done — MIG-A1 and DOC-A2 both shipped, so Phase 3’s entire Path-A GA scope is complete; Track B deferred to v1.1 (ADR-0010 Path A ratified 2026-07-06). Track B gained a ninth ticket (DIST-B9) on 2026-07-07. Owner: Engineering (Platform / Workflow) Last Updated: 2026-07-07


Phase 3 of PRD-003 §10scale & distribution (workstream WS-5). This is the one phase whose scope forked on the ADR-0010 decisionratified 2026-07-06 as Path A (single-node appliance for GA). The tickets are split into two tracks accordingly:

  • Track A — the entire Phase-3 GA scope (Path A ratified). Two tickets: a migration framework (because a Postgres-backed surface already ships) and an honesty correction to the docs/roadmap.
  • Track B — the v1.1 “Scale-Out” milestone. Wiring the distributed machinery that today exists solely as tested library code onto the default path, plus multi-replica correctness. Deferred out of GA by the ADR-0010 Path-A decision; scheduled as v1.1, gated on GA shipping. Do not start until then.

Every Track-A ticket is also a Track-B prerequisite — no throwaway work, per ADR-0010.

Scope boundary: real-scale capacity engineering (billions of memories, thousands of concurrent runs, the O(N) memory scan and checkpoint-growth ceilings — PP-14) is a PRD-003 §4.2 non-goal tracked as GA-001 / PRD-002 Scale work. Phase 3 delivers the wiring and correctness that capacity engineering later builds on; it does not itself chase throughput numbers. One bridging design ticket (SCALE-B8) captures the encryption-defeats-pushdown decision because it is a design choice, not a tuning knob.

Ticket format matches RM-GA-P1/ RM-GA-P2.


TRACK A (GA — both paths)
MIG-A1 (migration framework) ─ independent; required if any Postgres backend ships
DOC-A2 (honesty correction) ─ independent; required at GA under Path A
TRACK B (v1.1 Scale-Out — deferred out of GA, after GA ships)
DIST-B1 (env-select workflow Postgres) ──> DIST-B2 (queue/worker path) ──> DIST-B6 (multi-replica test)
DIST-B3 (control-plane shared backend) ──┬─> DIST-B6
DIST-B4 (KMS root injection-only) ───────┘
DIST-B5 (gateway fleet resilience wiring) ─ independent
DIST-B7 (Helm replicas>1 topology) ── depends on DIST-B3, DIST-B6
SCALE-B8 (encryption vs. pushdown design) ─ independent; bridges to PRD-002 scale

Critical path (Track B): DIST-B1 → DIST-B2 → DIST-B6, with DIST-B3/B4 as a parallel track that also feeds DIST-B6. All Track-B tickets depend on MIG-A1 (they introduce/evolve Postgres schema).


Track A — GA scope (required under both ADR-0010 paths)

Section titled “Track A — GA scope (required under both ADR-0010 paths)”

MIG-A1 [P1] — Versioned migration framework for all Postgres backends

Section titled “MIG-A1 [P1] — Versioned migration framework for all Postgres backends”

Problem. All three Postgres backends run inline CREATE TABLE IF NOT EXISTS + ad-hoc ALTER TABLE ADD COLUMN IF NOT EXISTS at connect time — crates/wovyr-workflow/src/postgres.rs:63-79, crates/wovyr-memory/src/backends.rs:78-93, crates/wovyr-marketplace/src/postgres.rs:44. No migration framework, no schema_version table, no down-path, and every binary runs DDL on startup (requiring DDL privileges in prod). Additive columns work; any rename/type change/index rebuild or old-binary-vs-new-schema rollback is undefined behavior. The marketplace Postgres backend already ships, so this is GA-relevant even under Path A. (PRD-003 R-5.3; closes PP-13, and the schema portion of PP-14.)

Change.

  • Adopt a versioned migration tool (e.g. refinery or sqlx migrate — pick one; both work with the workspace’s existing Postgres crates). Add a schema_version (or tool-managed _migrations) table.
  • Move each backend’s DDL into numbered migration files; connect verifies the schema is at the expected version and refuses to run against an unmigrated/newer schema (fail-closed), rather than silently CREATE TABLE IF NOT EXISTS.
  • Separate wovyr admin migrate (or a startup flag) from serve, so the serving path needs no DDL privilege.

Acceptance criteria.

  • A fresh database is brought up by the migrate step; serve against an unmigrated DB fails with a clear “run migrations” error, not a partial auto-DDL.
  • The capability-gated Postgres integration tests (workflow/memory/marketplace) run against a migrated schema in the CI service-container job (CI-901 from Phase 2).
  • A version-skew test: an old binary refuses a newer schema rather than corrupting it.

Files. crates/wovyr-workflow/src/postgres.rs, crates/wovyr-memory/src/backends.rs, crates/wovyr-marketplace/src/postgres.rs; migration files under each crate; apps/wovyr-cli/src/admin.rs (migrate command). Size. L. Depends on: Phase-2 CI-901 (to actually exercise the migrated backends). Blocks: all Track-B tickets.

Status: Done (2026-07-07). Adopted refinery. Each of the three backends’ connect() was rewritten to only ever read the applied schema version (fail-closed Error::Config on a mismatch, too old or too new) — run_migrations(database_url) is the sole DDL path now, wired into a new wovyr admin migrate --target <workflow|memory|marketplace> --database-url <url> command. Each crate migrates into its own distinct tracking table (wovyr_{workflow,memory,marketplace}_schema_history) so all three can share one physical database without colliding — verified necessary since CI’s service-container job points all three WOVYR_*_POSTGRES_URL env vars at the same Postgres instance. The version-skew acceptance criterion is proven by connect_refuses_a_schema_newer_than_this_binary_understands (wovyr-workflow/tests/postgres_store.rs), which inserts a fake future-version row directly into the tracking table and asserts connect refuses it; CI-901’s service-container job now runs the migrate command for all three schemas before the capability-gated integration tests.


DOC-A2 [P1] — Correct docs/roadmap/README to match the shipping binary

Section titled “DOC-A2 [P1] — Correct docs/roadmap/README to match the shipping binary”

Problem. The distributed-execution machinery (workflow PostgresStore, WorkQueue, Worker, leases, sharded partitions), Redis breakers, and the Qdrant semantic cache are positioned in docs/roadmap as platform capabilities, but no shipping binary wires themdefault_workflows_engine (crates/wovyr-server/src/lib.rs:496-524) hardwires FileStore, and with_redis_breakers/with_qdrant_semantic_cache (crates/wovyr-provider/src/gateway.rs:146,186) have zero references in wovyr-server or apps/. docs/12-deployment/{kubernetes,helm}.md describe an unbuilt multi-service split. Shipping GA while docs claim an unwired capability is itself a defect. (PRD-003 R-5.5; closes PP-06/PP-08 honesty.)

Change.

  • Under Path A: update the README, docs/12-deployment/*, and the roadmap to state plainly that (a) the deployment is single-node (replicas: 1 is a product statement — see the Helm chart), and (b) the workflow-Postgres / Redis-breaker / Qdrant-cache code is library-only, not wired into the shipping binary.
  • Cross-reference ADR-0010 as the decision of record. Mark the multi-service kubernetes.md/helm.md topology explicitly aspirational.
  • If ADR-0010 ratifies Path B instead, this ticket becomes “update docs to describe the now-wired distributed topology” — done as part of Track B rather than standalone.

Acceptance criteria.

  • A doc-lint / review pass confirms no doc claims a capability the shipping binary lacks; each such feature is labeled library-only with a pointer to its follow-on.
  • The Helm chart’s single-replica constraint is documented as intent, not a TODO.

Files. README.md, docs/12-deployment/*.md, docs/18-roadmap/v1.0.md, docs/03-workflow-engine/distributed-execution.md. Size. S. Depends on: ADR-0010 ratified.

Status: Done (2026-07-07). docs/18-roadmap/v1.0.md, docs/12-deployment/{kubernetes,helm,docker-compose}.md already stated this plainly. Corrected: README.md (a stale, never-updated doc claiming a gRPC/multi-image/NATS/OAuth2/knowledge-graph surface and a fictional crates/agent-runtime-style repo layout that hasn’t matched reality since before v0.1 — a much larger gap than this ticket anticipated), plus docs/12-deployment/{index,docker,terraform}.md and docs/03-workflow-engine/distributed-execution.md, each given a clear status-line disclaimer that the multi-service/distributed-scheduler/gRPC/ NATS surface they describe is long-term aspirational or unwired library code, cross-referencing ADR-0010 and this ticket doc’s Track B.


Track B — v1.1 “Scale-Out” (after GA)

Section titled “Track B — v1.1 “Scale-Out” (after GA)”

Gate: ADR-0010 ratified Path A, so Track B is confirmed out of GA scope and scheduled as the v1.1 “Scale-Out” milestone. Do not start until the GA milestone (Phases 1–2 + Phase-3 Track A) has shipped. (Reopening Track B into GA would require a new ADR superseding ADR-0010.)

DIST-B1 [P1] — Env-select a Postgres-backed workflow store in the server

Section titled “DIST-B1 [P1] — Env-select a Postgres-backed workflow store in the server”

Problem. default_workflows_engine unconditionally builds a FileStore (or in-memory fallback); the WOVYR_WORKFLOW_POSTGRES_URL env var is referenced only in tests (crates/wovyr-workflow/tests/postgres_store.rs), never in a binary. The PostgresStore (crates/wovyr-workflow/src/postgres.rs, connect/with_partitions) exists and is tested but unreachable. (PRD-003 R-5.1; closes PP-06.)

Change.

  • Mirror the marketplace pattern (crates/wovyr-server/src/marketplace.rs:76): when built with the postgres feature and WOVYR_WORKFLOW_POSTGRES_URL is set, back the engine with PostgresStore; else the file store. Forward the feature through the server’s Cargo.toml (postgres = [..., "wovyr-workflow/postgres"]).
  • Respect MIG-A1: connect verifies schema version, does not auto-DDL.

Acceptance criteria.

  • With the env var set, workflow events/checkpoints persist to Postgres (verified via the integration job); without it, behavior is unchanged (file store).

Files. crates/wovyr-server/src/lib.rs (default_workflows_engine), crates/wovyr-server/Cargo.toml. Size. M. Depends on: MIG-A1. Blocks: DIST-B2.


DIST-B2 [P1] — Route server-submitted workflows through the queue/worker/lease path

Section titled “DIST-B2 [P1] — Route server-submitted workflows through the queue/worker/lease path”

Problem. The server drives executions with a fire-and-forget tokio::spawn(engine.resume(...)) (crates/wovyr-server/src/workflow_runner.rs:300-302) — no lease guards it, so two replicas would double-drive one execution. The WorkQueue/Worker machinery (crates/wovyr-workflow/src/queue.rs, worker.rsWorker::new/with_partitions, PostgresStore FOR UPDATE SKIP LOCKED leasing) exists but the server doesn’t use it. This is what makes “exactly-once with horizontal scaling” real. (PRD-003 R-5.1; closes PP-06.)

Change.

  • On submit, Engine::start durably creates the execution and enqueues it; a pool of in-process Workers (or a separate worker binary) leases and drives executions via the idempotent resume, with lease-expiry reclaim.
  • Builds on Phase-2 EXE-602 (startup reclaim) — under Path B, startup reclaim becomes lease-reclaim rather than in-process re-drive.

Acceptance criteria.

  • Two server replicas against one Postgres run each execution exactly once (no duplicated activity effects); a killed worker’s lease expires and another reclaims and completes the run.

Files. crates/wovyr-server/src/workflow_runner.rs, lib.rs (worker pool in serve). Size. L. Depends on: DIST-B1. Blocks: DIST-B6.


DIST-B3 [P1] — Promote control-plane catalogs to a shared backend

Section titled “DIST-B3 [P1] — Promote control-plane catalogs to a shared backend”

Problem. Every control-plane catalog (tenancy, secrets, KMS, plugins, webhooks, audit, agents) is file-only under ~/.wovyr. Two replicas cannot share them, so tenancy/quotas/agents diverge across replicas. (PRD-003 R-5.2; closes PP-08.)

Change.

  • Behind the existing trait ports (TenancyStore, SecretStore, KmsStore, WebhookStore, AuditSink, and the persisted agent store from Phase-2 DUR-404), add Postgres-backed implementations selected by env (one WOVYR_*_POSTGRES_URL per catalog, or a shared connection). Reuse MIG-A1’s migration framework.
  • Prioritize the catalogs whose divergence is most harmful (tenancy, agents, audit).

Acceptance criteria.

  • Two replicas against one Postgres see the same tenancy/agents/audit state; a write on replica A is immediately visible on replica B.

Files. crates/wovyr-tenancy, wovyr-secrets, wovyr-kms, wovyr-events, wovyr-audit (Postgres impls); crates/wovyr-server/src/lib.rs (selection). Size. L. Depends on: MIG-A1, Phase-2 DUR-404. Blocks: DIST-B6, DIST-B7.


DIST-B4 [P1] — KMS root key injection-only in multi-replica mode

Section titled “DIST-B4 [P1] — KMS root key injection-only in multi-replica mode”

Problem. The KMS root key is generated-and-persisted per host at ~/.wovyr/kms/root.key if WOVYR_KMS_ROOT_KEY is unset (crates/wovyr-kms/src/root.rs, default_kms in crates/wovyr-server/src/lib.rs). With per-pod volumes, replica 2 generates its own root key and cannot decrypt replica 1’s sealed data — a silent, catastrophic split. (PRD-003 R-5.2; closes PP-08 for the crypto path.)

Change.

  • In multi-replica mode (detected via config, e.g. WOVYR_REPLICAS>1 or an explicit WOVYR_KMS_REQUIRE_INJECTED_ROOT=1), refuse to start without WOVYR_KMS_ROOT_KEY; never auto-generate. Builds on Phase-2 DR-1002 (escrow made mandatory).

Acceptance criteria.

  • Two replicas started with the same injected WOVYR_KMS_ROOT_KEY cross-decrypt each other’s sealed records; a replica with no injected key in multi-replica mode refuses to start.

Files. crates/wovyr-kms/src/root.rs, crates/wovyr-server/src/lib.rs. Size. S. Depends on: Phase-2 DR-1002. Blocks: DIST-B6.


DIST-B5 [P2] — Wire Redis breakers and Qdrant semantic cache into the gateway

Section titled “DIST-B5 [P2] — Wire Redis breakers and Qdrant semantic cache into the gateway”

Problem. Gateway::with_redis_breakers and with_qdrant_semantic_cache (crates/wovyr-provider/src/gateway.rs:146,186) provide fleet-shared circuit-breaker state and a shared semantic cache, but default_gateway never calls them. A fleet of gateways can’t trip/recover together or share cache entries. (PRD-003 R-5.4; closes PP-06 for the gateway path.)

Change.

  • In default_gateway, when WOVYR_REDIS_URL / WOVYR_QDRANT_URL (+ the relevant cargo features) are set, attach shared breakers and the Qdrant semantic cache; else the in-process defaults. KV/cache errors already fail open/degrade per the crate design.

Acceptance criteria.

  • With Redis configured, two gateways share breaker state (one tripping is visible to the other); with Qdrant configured, a cache entry written by one is served to the other.

Files. crates/wovyr-server/src/lib.rs (default_gateway), server Cargo.toml feature forwarding. Size. M. Depends on: none (independent Track-B item).


DIST-B6 [P1] — Multi-replica correctness test suite

Section titled “DIST-B6 [P1] — Multi-replica correctness test suite”

Problem. Nothing proves ≥2 replicas behave correctly against shared state — the core claim Path B exists to deliver. (PRD-003 R-5.1/R-5.2 verification; closes PP-08.)

Change.

  • An integration test (docker-compose or a two-process harness) runs two wovyr replicas against one Postgres (+ Redis/Qdrant), and asserts: shared tenancy/agents/ audit, exactly-once workflow execution under concurrent submit, replica-crash mid-workflow reclaim-and-complete, and cross-replica KMS decryption.

Acceptance criteria.

  • The suite passes in CI’s service-container job; killing one replica mid-workflow does not lose or duplicate work.

Files. crates/wovyr-server/tests/multi_replica.rs (new); CI job. Size. L. Depends on: DIST-B2, DIST-B3, DIST-B4.


DIST-B7 [P2] — Helm chart multi-replica topology

Section titled “DIST-B7 [P2] — Helm chart multi-replica topology”

Problem. The Helm chart pins replicas: 1 (deployment/helm/wovyr/templates/wovyr-statefulset.yaml) because durable state is local files. Once DIST-B3 makes state shared, the chart can scale out. (PRD-003 R-5.2 deployment; closes PP-08 deployment.)

Change.

  • Add a Deployment (or scalable StatefulSet) topology gated on shared-backend config: replicas > 1 requires the Postgres/Redis/Qdrant URLs and injected KMS root (DIST-B4). Validate offline with helm lint/kubeconform (the existing chart’s precedent).

Acceptance criteria.

  • helm template with a multi-replica values file renders a valid, schema-checked manifest that wires the shared backends and injected KMS root; single-replica remains the default.

Files. deployment/helm/wovyr/. Size. M. Depends on: DIST-B3, DIST-B6.


DIST-B9 [P2] — Cross-replica distributed event bus

Section titled “DIST-B9 [P2] — Cross-replica distributed event bus”

Problem. wovyr-events is a custom in-process event/webhook/audit system — correct and sufficient for the single-node appliance (ADR-0010 Path A), but it has no way to fan an event out to other replicas. ADR-0005 decided NATS JetStream for this back on 2026-06-27, but the decision was never executed and nothing else in this Track-B list picks it up: DIST-B3 shares control-plane catalogs (config/state) via Postgres, not real-time event distribution. Once ≥2 replicas exist, a workflow event emitted on replica A that a subscriber on replica B needs to react to (or a webhook delivery that must not be double-fired by both replicas) has no cross-process path today. Found while reconciling the Day-1 architecture docs against ADR-0010’s Path A reality (2026-07-07); not a PP-numbered finding from the original 2026-07-06 review, since that review scoped WS-5 to the workflow-execution and gateway-resilience backends specifically, not general async messaging.

Change.

  • Stand up a NATS JetStream backend behind a new port trait alongside wovyr-events’s existing WebhookStore/dispatch abstractions (mirroring how wovyr-provider’s with_redis_breakers sits behind the Gateway rather than replacing it): default_event_bus selects NATS when WOVYR_NATS_URL (+ a nats cargo feature) is set, else the existing in-process dispatch. Deduplicate on the consumer side by request_id/event id — JetStream is at-least-once, not exactly-once, exactly as ADR-0005’s original consequences section anticipated.

Acceptance criteria.

  • With WOVYR_NATS_URL configured, an event emitted by one server process is observed by a subscriber on a second, independent process; without it, behavior is unchanged from today’s in-process dispatch.

Files. crates/wovyr-events/src/ (new NATS backend + port trait); crates/wovyr-server/src/lib.rs (selection); workspace Cargo.toml (nats feature). Size. L. Depends on: DIST-B3 (shared control-plane state is the more foundational Track-B prerequisite; this is independent but more valuable once it exists).


SCALE-B8 [P2] — Design: preserve retrieval pushdown under memory encryption

Section titled “SCALE-B8 [P2] — Design: preserve retrieval pushdown under memory encryption”

Problem. The server always wraps memory in EncryptingMemoryStore, which unconditionally reports supports_pushdown() = false (documented design), so even a Qdrant-backed tiered store degrades to a full all() scan + in-process decrypt + O(N) cosine (crates/wovyr-memory/src/engine.rs:203-205). This caps practical retrieval at ~10³–10⁴ records/namespace — a design choice (correct-but-slow) that becomes the binding constraint the moment PRD-002’s real-scale work starts. This ticket decides the design, it does not chase throughput. (Bridges PP-08/PP-14 to GA-001/PRD-002.)

Change.

  • Evaluate options and record a decision (short ADR): encrypt content but leave embeddings plaintext so the index can score them (with a documented threat-model note), vs. a searchable-encryption scheme, vs. accepting the scan ceiling for the single-node appliance. Whichever is chosen, the O(N) put seq re-read (crates/wovyr-memory/src/store.rs) is fixed with a per-namespace counter.

Acceptance criteria.

  • A decision ADR exists with the threat-model trade-off stated; if “embeddings plaintext” is chosen, pushdown survives encryption and a perf test shows sub-linear retrieval on a Qdrant-backed encrypted namespace.

Files. new ADR under docs/17-adr/; crates/wovyr-memory/src/encrypting_store.rs, engine.rs, store.rs. Size. M (design) + follow-on. Depends on: none. (Hand-off point to PRD-002 Scale / GA-001.)


TicketTrackTitleSizePriorityDepends on
MIG-A1A (GA)Postgres migration framework — DoneLP1Phase-2 CI-901
DOC-A2A (GA)Docs/roadmap honesty correction — DoneSP1ADR-0010
DIST-B1B (v1.1)Env-select workflow Postgres storeMP1MIG-A1
DIST-B2B (v1.1)Queue/worker/lease execution pathLP1DIST-B1
DIST-B3B (v1.1)Control-plane shared backendLP1MIG-A1, DUR-404
DIST-B4B (v1.1)KMS root injection-only (multi-replica)SP1DR-1002
DIST-B5B (v1.1)Redis breakers + Qdrant cache wiringMP2
DIST-B6B (v1.1)Multi-replica correctness testsLP1B2, B3, B4
DIST-B7B (v1.1)Helm multi-replica topologyMP2B3, B6
DIST-B9B (v1.1)Cross-replica distributed event bus (NATS)LP2DIST-B3
SCALE-B8B (bridge)Encryption-vs-pushdown design ADRMP2

Track A total (GA): 1 L + 1 S ≈ 1.5–2 engineer-weeks. This is all Phase 3 needs for a Path-A GA. Track B total (v1.1): 5 L + 2 M + 1 S + SCALE-B8 ≈ 12–16 engineer-weeks, parallelizable to ~6–7 calendar weeks (workflow track vs. control-plane track are independent until DIST-B6; DIST-B9 is independent of both but more valuable once DIST-B3 lands). DIST-B9 added 2026-07-07, discovered while reconciling ADR-0005 against ADR-0010’s Path A reality — not part of the original 21-finding review.

Phase-3 exit (GA / Path A) — met (2026-07-07): PRD-003 §11 item 4 — no doc or roadmap claims a capability the shipping binary lacks (DOC-A2), and every shipped Postgres surface has real, versioned migrations (MIG-A1). Phase-3 exit (v1.1 / Path B) = two replicas share state and survive a replica crash mid-workflow with exactly-once effects — Track B, not started, gated on the GA milestone shipping.



VersionDateDescription
1.4.02026-07-07Added Track-B ticket DIST-B9 (cross-replica distributed event bus / NATS) — found while reconciling the Day-1 architecture docs (docs/02-architecture/) against ADR-0010’s Path A reality: ADR-0005 decided NATS in 2026-06-27 but it was never implemented and nothing else in Track B picks it up. Not part of the original 21-finding review; added so the gap is deferred deliberately, not silently dropped
1.3.02026-07-07MIG-A1 done: adopted refinery for all three Postgres backends (workflow/memory/marketplace) — versioned migration files, fail-closed schema-version checks on connect, a new wovyr admin migrate command, and a version-skew test. Phase 3’s entire Path-A GA scope is now complete
1.2.02026-07-07DOC-A2 done: corrected README.md (a much larger, long-stale gap than anticipated), docs/12-deployment/{index,docker,terraform}.md, and docs/03-workflow-engine/distributed-execution.md to state plainly what’s shipped vs. aspirational/library-only
1.1.02026-07-06ADR-0010 ratified Path A: Track A confirmed as the entire Phase-3 GA scope; Track B confirmed deferred to the v1.1 “Scale-Out” milestone (status/gate wording updated accordingly)
1.0.02026-07-06Initial Phase-3 (scale & distribution) ticket breakdown: 2 Track-A (GA, both paths) + 8 Track-B (v1.1 Scale-Out, Path B only) tickets, gated on the ADR-0010 decision, with the real-scale-capacity boundary handed off to PRD-002/GA-001